Delivery Plan
Planned Delivery dates
Phase 1 :
Phase 2 :
Phase 3 :
| Epic | Story | Phase 1 | Phase 2 | Phase 3 |
|---|---|---|---|---|
| Manage Reference Data | UC02 Create observatory admin | Phase 1 | ||
| UC03 Configure observatory | Phase 1 | |||
| UC 04 Create new proposal cycle | Phase 1 | |||
| UC08 Create TAC Chair | Phase 2 | |||
| UC09 Add TAC members | Phase 2 | |||
| UC16 Assign internal reviewer | Phase 2 | |||
| UC17 Assign external reviewer | Phase 2 | |||
| Deploy System | UC00 Deploy the system | Phase 1 | ||
| UC01 User registers to the system | Phase 1 | |||
| Assemble Proposal | UC05 Create observing proposal | Phase 1 | ||
| UC06 Edit observing proposal | Phase 1 | |||
| UC07 Submit a proposal | Phase 1 | |||
| UC15 Import whole proposal | Phase 2 | |||
| UC20 Clone proposal | Phase 2 | |||
| UC21 Withdraw proposal | Phase 3 | |||
| Consider Proposal | UC10 Review proposals | Phase 2 | ||
| UC11 Score proposals | Phase 2 | |||
| UC12 Assign observing time | Phase 2 | |||
| UC13 Inform PIs about allocation | Phase 3 | |||
| UC18 Review proposal scores | Phase 2 | |||
| UC22 Revoke allocation | Phase 3 | |||
| Common | UC14 Export whole proposal | Phase 2 | ||
| Manage Hardware | Procure, configure, and deliver Dev application servers,with agreed standby | Phase 1 | ||
| Procure, configure, and deliver Stage and Production application servers, with agreed standby | Phase 2 | |||
| Manage DBMS | Procure, configure, and deliver Dev database servers, with agreed standby | Phase 1 | ||
| Procure, configure, and deliver Stage and Production database servers, with agreed standby | Phase 2 | |||
| Implement database security | Phase 1 | |||
| Implement agreed data backup strategy | Phase 1 | |||
| Statistics | Monitor Production system usage | Phase 3 |